(@monvillemauro)
Noble Member
Joined: 2 years ago
Posts: 721
Topic starter  

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

  • A . Schedule meetings with all of the stakeholders to make business decisions when needed.
  • B . Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.
  • C . Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.
  • D . Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

Show Answer Hide Answer

Suggested Answer: C

   