An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.
How should the project manager ensure that the client is effectively represented in the daily meetings?
- A . Recommend agile training programs that best suit the client project manager's schedule.
- B . Realign the project to a predictive approach to ensure optimal collaboration between the teams.
- C . Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals
- D . Provide the client project manager with agile best practice documents and web resources.
Suggested Answer: A