Eight people have been working on a project for an extended period of time. The scope has changed significantly and the product owner has been replaced multiple times. The team members are feeling disassociated from the project.
What should the project manager do to ensure team alignment with the goals?
- A . Ask the new product owner to explain the importance of the project.
- B . Email the team a detailed outline of the business requirements.
- C . Review the project charter with the team.
- D . Facilitate a discussion of the vision for the project.
Suggested Answer: D