A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
- A . Request for information
- B . Scope statement
- C . Issue log
- D . Risk register
Suggested Answer: D