A contractor delivering construction services to a company is using agile principles to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design changes or performing rework.
What should the project manager do to minimize the cost?
- A . Put the project on hold until all definitions are ready in order to avoid rework.
- B . Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.
- C . Capture the engineers' feedback at the daily meeting and communicate it to the product owner.
- D . Cancel the project release resources, then start again when all the definitions are ready.
Suggested Answer: B