An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work.
What should the project manager do?
- A . Ask for additional team members to maintain the velocity
- B . Implement a checkpoint in the iteration to verify if the team is on track
- C . Conduct a focused retrospective to help the team to discover the root cause
- D . Ask the team to have a lower commitment for the next iteration
Suggested Answer: D