Notifications
Clear all
Topic starter
11/07/2022 5:03 pm
One of the service providers on a complex project has been facing resource availability problems over the last six months. However, the service provider has assured the project manager that the deliverables will be on time.
How should the project manager address this situation?
- A . Update the issue log.
- B . Perform a qualitative risk analysis.
- C . Perform a root cause analysis.
- D . Implement a risk response plan.
Suggested Answer: A