In order to ensure the project is following the compliance requirements, what should the project manager do?

1 Posts
1 Users
0 Likes
177 Views
(@casausisaiah)
Noble Member
Joined: 2 years ago
Posts: 710
Topic starter  

A project manager is leading an agile project in an organization that has not executed this type of project before.

In order to ensure the project is following the compliance requirements, what should the project manager do?

  • A . Follow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.
  • B . Use the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.
  • C . Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.
  • D . Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Show Answer Hide Answer

Suggested Answer: C

   