A new relevant project stakeholder suggested a change to some of the project parameters midway through execution.
What should the project manager do next?
- A . Accept the change and use contingency funds to implement this change with minimal schedule impacts
- B . Reject the change because it is contrary to what was agreed to during earlier phases of the project
- C . Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps
- D . Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor
Suggested Answer: D