A project manager works at an organization that is transitioning to agile. The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
- A . Advise the project management office (PMO) to use the burndown chart as the single communication channel.
- B . Develop a communications management plan for each category in the stakeholder register.
- C . Include the burndown chart in a monthly report that is distributed to all stakeholders.
- D . Postpone the recommendation since the organization does not currently have a defined agile methodology.
Suggested Answer: A