What should the team do next?

1 Posts
1 Users
0 Likes
305 Views
(@tivisantwan)
Noble Member
Joined: 2 years ago
Posts: 716
Topic starter  

During an iteration demo, a customer noticed an enhancement they would like to make to the product .

What should the team do next?

  • A . Refine and estimate the enhancement so the size is known.
  • B . Add it to the product backlog to be completed in the future.
  • C . Start working on the enhancement for the customer immediately.
  • D . Ask the product owner to prioritize the item with the customer.

Show Answer Hide Answer

Suggested Answer: D

   