While working on a poorly defined internal project, a project manager receives multiple change requests from senior management .
What should the project manager do first?
- A . Identify how the proposed changes will benefit the project in relation to the business case.
- B . Ask for a temporary budget increase to avoid cost overruns.
- C . Keep the team motivated and incentivized to avoid exhaustion from working on a lengthy project.
- D . Assess the schedule delay and begin implementation to avoid additional lags
Suggested Answer: A