A project management team received news that a competitor has released the latest version of a program .
What should the team do next?
- A . Review the project plan to evaluate if any updates should be made.
- B . Crash the existing schedule with additional resources to deliver more features.
- C . Stop the project immediately as the market opportunity has already been missed.
- D . Continue with the project plan and target delivery date as expected.
Suggested Answer: A