During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year .
What should the project manager do?
- A . Promote a productive environment where everybody can work without interruptions from the rest of the team members.
- B . Create a reward system recognizing group contributions to get people motivated and improve performance.
- C . Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP).
- D . Design a set of metrics including velocity, which is a good measure of value delivered.
Suggested Answer: C