A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.
What should the project manager do?
- A . Ask to execute the project with a predictive approach since there is a budget and schedule risk
- B . agile tools and techniques used m the defined hybrid methodology for consistent application by all team members
- C . Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices
- D . Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update
Suggested Answer: B