During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
- A . Include additional mitigation actions against feature defects and update the risk management plan.
- B . Assess the relevance of the feature and then analyze the submission of a change request to descope it.
- C . Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.
- D . Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.
Suggested Answer: A