What should the project manager do next?

1 Posts
1 Users
0 Likes
139 Views
(@mcgruenathaniel)
Noble Member
Joined: 2 years ago
Posts: 732
Topic starter  

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

  • A . Include additional mitigation actions against feature defects and update the risk management plan.
  • B . Assess the relevance of the feature and then analyze the submission of a change request to descope it.
  • C . Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.
  • D . Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Show Answer Hide Answer

Suggested Answer: A

   