A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.
What should have been done to avoid this problem?
- A . Included lessons learned from past projects
- B . Used bottom-up estimating
- C . Utilized three-point estimates
- D . Validated the schedule performance index (SPI) to evaluate deviation
Suggested Answer: C