A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current.
Which action should the project manager take?
- A . Create a specific sprint to deliver the project documentation.
- B . Assign a dedicated resource to work on the documentation during the project.
- C . Make documentation a standard part of the definition of done (DoD).
- D . Focus on the documentation after the features are delivered.
Suggested Answer: C