Which action should the project manager take?

1 Posts
1 Users
0 Likes
199 Views
(@colmenerocarmelo)
Noble Member
Joined: 2 years ago
Posts: 746
Topic starter  

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

  • A . Create a specific sprint to deliver the project documentation.
  • B . Assign a dedicated resource to work on the documentation during the project.
  • C . Make documentation a standard part of the definition of done (DoD).
  • D . Focus on the documentation after the features are delivered.

Show Answer Hide Answer

Suggested Answer: C

   