An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

  • A . Add 4 additional weeks to the schedule and request additional resources.
  • B . Ask the sponsor to obtain a special work permit to continue work.
  • C . Review the project management plan to see the impact of the possible delay.
  • D . Crash the resource management plan to keep the schedule on track.

Show Answer Hide Answer

Suggested Answer: B

   
Quote
(@rajeshtk)
New Member
Joined: 2 years ago
Posts: 2
 

C is the correct answer


   