An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.
What should the project manager do?
- A . Add 4 additional weeks to the schedule and request additional resources.
- B . Ask the sponsor to obtain a special work permit to continue work.
- C . Review the project management plan to see the impact of the possible delay.
- D . Crash the resource management plan to keep the schedule on track.
Suggested Answer: B
10/10/2022 8:02 pm
C is the correct answer