What is the first thing the project manager should do"?

1 Posts
1 Users
0 Likes
73 Views
(@ruleychuck)
Noble Member
Joined: 2 years ago
Posts: 689
Topic starter  

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

  • A . Include the requirement into the project and schedule it as soon as possible
  • B . Inform the project sponsor about the situation and request assistance
  • C . Evaluate the impact that the inclusion of this new requirement will have on project performance
  • D . Inform the stakeholder that it is impossible to add new requirements to an approved
    project scope

Show Answer Hide Answer

Suggested Answer: C

   