What should the pro...
 
Notifications
Clear all

What should the project manager do?

1 Posts
1 Users
0 Likes
140 Views
(@pesterfieldrayford)
Noble Member
Joined: 2 years ago
Posts: 681
Topic starter  

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected.

What should the project manager do?

  • A . Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project
  • B . Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes
  • C . Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.
  • D . Explain that distribution of important news can only be done using traceable communication methods

Show Answer Hide Answer

Suggested Answer: A

   
Quote

Latest PMP V1 Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: