A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
What are the first two actions the project manager should perform? (Choose two)
- A . Create a change request to discuss with the change control board (CCB).
- B . Request additional budget for contingency.
- C . Perform a risk identification process with the project team.
- D . Consult with the project stakeholders.
- E . Discuss the possible impacts with subject matter experts (SMEs).
Suggested Answer: A,B