A program manager takes over a global program from another program manager. Upon arriving on-site, the program manager immediately sees that stakeholders are upset because of a lack of updates and communications about the program.
What should the program manager do first?
- A . Review the program governance plan and communication log
B. Review the program communications management plan and stakeholder register
C. Review the stakeholder engagement plan and stakeholder matrix
D. Notify the executive sponsor and update the program issue tog
Suggested Answer: B