When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)

1 Posts
1 Users
0 Likes
230 Views
(@colmenerocarmelo)
Posts: 746
Noble Member
Topic starter
 

When responding to a submittal that has been rejected and/or has comments written by a reviewer, the ICT distribution designer may need to perform which two of the following actions? (Select two options.)

  • A . Request a Change Order from the client for the extra work performed.
    B. Document the reviewer's status and/or comments
    C. Review the contract requirements and revise the submittal to comply with these requirements
    D. Request a variance from the contract requirements from the client.
    E. Submit an alternate product in lieu of one that was previously submitted, even if it does not meet all of the contract requirements

Show Answer Hide Answer

Suggested Answer: D, E
 