What strategy should the project manager implement to deal with this situation?

1 Posts
1 Users
0 Likes
202 Views
(@ripaharris)
Noble Member
Joined: 2 years ago
Posts: 737
Topic starter  

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

  • A . Ask the team.to accelerate the iterations and avoid interruptions.
  • B . Discuss the problem with the team and decide how to do the work together.
  • C . Verify team performance and ask for improvement during daily standup meetings.
  • D . Recommend that the project sponsor increases the budget to bring new resources.

Show Answer Hide Answer

Suggested Answer: D

   