A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue .
What should the project manager do?
- A . Discuss with the product owner that the user story will not be completed this iteration.
- B . Meet with the team member's functional manager to try to remove the impediment.
- C . Tell the project team member not to work on the production issue and to inform their manager.
- D . Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.
Suggested Answer: B