What should the project team have done to avoid this issue?

1 Posts
1 Users
0 Likes
197 Views
(@castilogonzalo)
Noble Member
Joined: 2 years ago
Posts: 663
Topic starter  

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

  • A . Held a touchpoint with marketing before the demo to discuss any impediments
  • B . Scheduled a demo presentation of the product during the first reason
  • C . Asked the marketing team to start working on the product immediately
  • D . Confirmed marketing requirements and constraints when adding to the backlog

Show Answer Hide Answer

Suggested Answer: A

   