A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed .
What should the team do to assess and manage risks regularly?
- A . Identify and escalate any identified risks to the facilitator to handle
- B . Update the risk register during every iteration with any open concerns
- C . Use regular feedback loops through daily standups iteration demos and retrospectives
- D . Focus on developing a working deliverable instead of documenting risks
Suggested Answer: C