When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a result, the team ground rules favor these two team members.
What should the project manager have done to avoid this situation?
- A . Come to the meeting with suggested ground rules
- B . Ask all team members to send new ideas prior to the meeting
- C . Extend the meeting to allow everyone to speak
- D . Set expectations for contributions ahead of the meeting
Suggested Answer: D