A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project
and the customer.
What should the project manager do?
- A . Ask the team member to submit a formal change request.
- B . Accept the suggestion as it has no impact on the project.
- C . Ask another team member to validate the impacts of the suggestion.
- D . Reject the suggestion and ask the team member to focus on executing the plan.
Suggested Answer: A