What should the project manager do?

1 Posts
1 Users
0 Likes
200 Views
(@rippesteban)
Noble Member
Joined: 2 years ago
Posts: 727
Topic starter  

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project

and the customer.

What should the project manager do?

  • A . Ask the team member to submit a formal change request.
  • B . Accept the suggestion as it has no impact on the project.
  • C . Ask another team member to validate the impacts of the suggestion.
  • D . Reject the suggestion and ask the team member to focus on executing the plan.

Show Answer Hide Answer

Suggested Answer: A

   