What should the project manager do to address this situation?

1 Posts
1 Users
0 Likes
285 Views
 Chi
(@jamiesonchi)
Noble Member
Joined: 2 years ago
Posts: 727
Topic starter  

A project manager finds out that the required project status reports have not been filled out by most team members. These status reports are urgently needed to compile a comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

  • A . Reprimand the team members who did not fill out the status reports.
  • B . Justify the team members' behavior to the project sponsor.
  • C . Quickly put together a report that will satisfy the project sponsor.
  • D . Discuss the issue with the team members at fault.

Show Answer Hide Answer

Suggested Answer: D

   