What should the project manager do next?

1 Posts
1 Users
0 Likes
235 Views
(@hevesywilber)
Noble Member
Joined: 2 years ago
Posts: 682
Topic starter  

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.

What should the project manager do next?

  • A . Update the risk register to reflect the delay, communicate the impact to the schedule, and escalate to management for assistance.
  • B . Conduct a project review with the project sponsor to explain the delay and add a developer to work with the vendor.
  • C . Review the contract with the vendor to go over the financial penalty that is applicable to this situation.
  • D . Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track.

Show Answer Hide Answer

Suggested Answer: D

   