What should the project manager have done to avoid this situation?

1 Posts
1 Users
0 Likes
307 Views
 Ali
(@ferdigali)
Noble Member
Joined: 2 years ago
Posts: 698
Topic starter  

A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.

What should the project manager have done to avoid this situation?

  • A . Allocated a dedicated handover team at early stages of the project
  • B . Allocated proper resources for training on BMS in the project plan
  • C . Made some adjustments to BMS to be more suitable for the teams
  • D . Brought both teams together in a joint meeting to resolve the issue

Show Answer Hide Answer

Suggested Answer: D

   