10/05/2022 5:52 am
A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team
What should the project manager do first to ensure the project is compliant?
- A . Meet with the team to discuss compliance concerns
- B . Review the organizational process assets (OPAs) for compliance topics
- C . Review the compliance strategy and version history
- D . Meet with the project sponsor to discuss their compliance concerns
Suggested Answer: C