A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.
What should the project manager do first?
- A . Accept the feature.
- B . Determine if the feature is within the scope.
- C . Submit a change request! for the feature.
- D . Reject the feature.
Suggested Answer: B