A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.
What should the project manager do?
- A . Study and determine the appropriate leadership style suitable for the team.
- B . Hire a project team leader who can influence the project team members.
- C . Schedule a meeting and communicate the performance concern to the team.
- D . Apply an agile approach to help improve team performance.
Suggested Answer: A