A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own
What should the project manager do?
- A . Improve the risk management strategy and risk monitoring
- B . Reach out to the project manager of the previous project for assistance
- C . Allow the team member to work through the issue as a training opportunity
- D . Share the lessons learned from the previous protect with the team member
Suggested Answer: D