Notifications
Clear all
Topic starter
15/07/2022 6:30 am
A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority .
What should the new project manager do next?
- A . Refer to the project charter
- B . Review the project resource matrix
- C . Assess the stakeholder register
- D . Update the communications management plan
Suggested Answer: A