What should the new project manager do next?

1 Posts
1 Users
0 Likes
153 Views
(@siwekphilip)
Noble Member
Joined: 2 years ago
Posts: 730
Topic starter  

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority .

What should the new project manager do next?

  • A . Refer to the project charter
  • B . Review the project resource matrix
  • C . Assess the stakeholder register
  • D . Update the communications management plan

Show Answer Hide Answer

Suggested Answer: A

   