The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)

  • A . Inform the customer that moving the milestone has a very high impact on project cost.
  • B . Escalate the Issue to senior management so they can impose a solution on the customer.
  • C . Convince the customer to keep the requirements as is and not move the milestone.
  • D . Review the customer's priorities regarding the desired requirements for the milestones.
  • E . Discuss which requirements can be delivered faster with the project team.

Show Answer Hide Answer

Suggested Answer: D,E

   