Notifications
Clear all
Topic starter
03/11/2022 9:03 pm
During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays.
What should the project manager have done to manage the issue?
- A . Identified and reported the issue
- B . Monitored and controlled the issue
- C . Identified the appropriate response and had it implemented
- D . Communicated any identified action to impacted stakeholders
Suggested Answer: B