During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays.

What should the project manager have done to manage the issue?

  • A . Identified and reported the issue
  • B . Monitored and controlled the issue
  • C . Identified the appropriate response and had it implemented
  • D . Communicated any identified action to impacted stakeholders

Show Answer Hide Answer

Suggested Answer: B

   