Which action should the project manager take next?

1 Posts
1 Users
0 Likes
128 Views
(@palomamikel)
Noble Member
Joined: 2 years ago
Posts: 733
Topic starter  

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

  • A . Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.
  • B . Ask the team to wait until they are able to update the requirements specifications.
  • C . Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.
  • D . Meet with the development team to review and assess the requirements specifications.

Show Answer Hide Answer

Suggested Answer: D

   