A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.
Which action should the project manager take next?
- A . Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.
- B . Ask the team to wait until they are able to update the requirements specifications.
- C . Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.
- D . Meet with the development team to review and assess the requirements specifications.
Suggested Answer: D