What should the project manager do?

1 Posts
1 Users
0 Likes
155 Views
(@whellerrashad)
Noble Member
Joined: 2 years ago
Posts: 729
Topic starter  

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

  • A . Prioritize which backlog activities should be kept.
  • B . Work on the backlog activities with fewer story points.
  • C . Ask for more resources to clear the backlog activities.
  • D . Assign an owner for each backlog activity and track progress.

Show Answer Hide Answer

Suggested Answer: D

   