Notifications
Clear all
Topic starter
14/08/2022 6:01 am
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
- A . Prioritize which backlog activities should be kept.
- B . Work on the backlog activities with fewer story points.
- C . Ask for more resources to clear the backlog activities.
- D . Assign an owner for each backlog activity and track progress.
Suggested Answer: D