What should the pro...
 
Notifications
Clear all

What should the project manager have the project team do first to address the issue?

1 Posts
1 Users
0 Likes
70 Views
(@casausisaiah)
Noble Member
Joined: 2 years ago
Posts: 710
Topic starter  

During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected.

What should the project manager have the project team do first to address the issue?

  • A . Update the issue log and document the change
  • B . Review the product specification requirements.
  • C . Perform a root cause analysis
  • D . Submit a change request for corrective action.

Show Answer Hide Answer

Suggested Answer: C

   
Quote

Latest PMP V1 Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: