A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype
What should the project manager do to accelerate this solution?
- A . Contact the other project team and ask them to organize a demo of the prototype
- B . Perform iterative planning with the team to use the prototype
- C . Check the burnup charts to see what progress has been made to integrate the solution
- D . Prioritize the backlog with the customer to remove the feature
Suggested Answer: A