What should the project manager do to resolve this?

1 Posts
1 Users
0 Likes
266 Views
(@baumgarnerisreal)
Noble Member
Joined: 2 years ago
Posts: 677
Topic starter  

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

  • A . Meet with the stakeholder to discuss the impact of the deliverable
  • B . Consider the stakeholder as a risk and evaluate possible solutions with the project team
  • C . Improve communication with the stakeholder to obtain their assistance in the future
  • D . Escalate to the project sponsor due to the political nature of the issue

Show Answer Hide Answer

Suggested Answer: D

   