19/08/2022 2:18 pm
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable
What should the project manager do to resolve this?
- A . Meet with the stakeholder to discuss the impact of the deliverable
- B . Consider the stakeholder as a risk and evaluate possible solutions with the project team
- C . Improve communication with the stakeholder to obtain their assistance in the future
- D . Escalate to the project sponsor due to the political nature of the issue
Suggested Answer: D