In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan
What should the project manager do?
- A . Update the risk register including noncompliance with the change process as a probable cause for scope creep
- B . Make sure that all stakeholders are aware and in agreement with the project governance structure m place
- C . Advise the team not to engage in modifications unless it follows the proper change approval process
- D . Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced
Suggested Answer: B