A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities
What should the project manager do next?
- A . Document the project management plans and share them with the company and all team members via email for review
- B . Create a log to track risks assumptions issues and dependencies and establish a periodic review with the stakeholders
- C . Add contingency m the schedule to account for dependencies and risks then review rt with the team
- D . Engage with the company and the project team to determine the best course of action
Suggested Answer: B