What should the project manager do?

1 Posts
1 Users
0 Likes
237 Views
(@pacapacmorgan)
Noble Member
Joined: 2 years ago
Posts: 738
Topic starter  

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?

  • A . Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively
  • B . Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training
  • C . Make sure all stakeholders have access to the system and know where to find project artifacts
  • D . Send the project schedule via email to the stakeholders who need that information

Show Answer Hide Answer

Suggested Answer: C

   