A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule
What should the project manager do?
- A . Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively
- B . Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training
- C . Make sure all stakeholders have access to the system and know where to find project artifacts
- D . Send the project schedule via email to the stakeholders who need that information
Suggested Answer: C