06/11/2022 6:39 am
The team architect resigned from the company. The new architect points out a design flaw during a planning meeting that may potentially impact the final quality.
What should the project manager do first?
- A . Review the scope management plan.
- B . Update the design with changes.
- C . Request an architecture review.
- D . Update the quality management plan
Suggested Answer: C