What should the project leader do to improve the situation?

1 Posts
1 Users
0 Likes
169 Views
 Chi
(@jamiesonchi)
Noble Member
Joined: 2 years ago
Posts: 727
Topic starter  

A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team .

What should the project leader do to improve the situation?

  • A . Invest in developing the team's emotional intelligence.
  • B . Ask the unmotivated team member to take a short leave.
  • C . Reduce the number of daily and retrospective meetings.
  • D . Send the unmotivated team member to another team.

Show Answer Hide Answer

Suggested Answer: A

   